Thứ Tư, 29 tháng 5, 2013

Estimating Might Be Broken, But It’s Not Evil

Ron Jeffries's essay Estimation is Evil talks about how absurd estimating can be on a software project, and the nightmare scenarios that teams can end up in:
…Then we demand that the developers “estimate” when they’ll be done with all this stuff. They, too, know less about this product than they ever will again, and they don’t understand most of these requirements very well. But they do their best and they come up with a date. Does the business accept this date? Of course not! First of all, it’s only an estimate. Second, clearly the developers would leave themselves plenty of slack—they always do. Third, that’s not when we want it. We want it sooner.

So we push back on the developers’ estimate, leaning harder and harder until we’re sure we’ve squeezed out all the fat they left in there. Sometimes we even just tell them when they have to be done.

Either way, the developers leave the room, heads down, quite sure that they have again been asked to do the impossible. And the business people write down the date: “Development swears they’ll be done November 13th at 12:25PM.”

Software Estimation is Broken

Software Estimation – the way that most of us do it – is broken. As an industry we’re bad at estimating, we've been bad at it for a long time, and there’s no evidence that we’re getting much better at it.

Developers know this. The business knows this – so they don’t trust what the development team comes up with, and try to make their own plans. Management knows this too, so they work around estimates (I’ll take everything and double it), or worse they abuse estimates, cut them to the bone, and then use them as a lever to drive the team towards an unachievable goal.

Jeffries says that even teams who are trying to estimate properly are excessively concerned with predictability (and all of the overheads and navel gazing that come with trying to be predictable), when they really should be working on getting the right things done as soon as possible, which is all that the business actually cares about.

So because it’s hard, and because we’re not good at it, and because some people ignore estimates or abuse them, we should stop estimating at all.

As developers what we need to do is make sure that we understand what the most important thing is to the business, break the problem down into the smallest pieces possible and start iterating right away, deliver something and then go onto the next most important thing, and keep going until the business gets what they really need. If you can’t convince “them” (the sponsors) that this is the right way to work, then go through the theatre of estimating to get the project approved (knowing that whatever you come up with is going to be wrong and anyways management and the business are going to ignore it or use it against you), and then get to real work: understand what the most important thing is to the business, break the problem down into the smallest pieces possible and start iterating right away. In other words

“Stop estimating. Start Shipping”.

Martin Fowler wrote a recent post PurposeofEstimation where he says estimates are needed only if they help you make “significant decisions”. His examples are getting resources allocated (portfolio management go/no go – the game Jeffries describes above), and coordination, where your team's work needs to fit in with other teams (although he talks only about coordinating with other developers, ignoring the need to coordinate with customers, partners and other projects that have nothing to do with software development). There are many other times when estimates are needed: delivering to fixed-price contracts, budgeting for programs, when you need to hit a drop dead date (for example, when an industry-wide change is going to happen whether you are done or not).

The rest of the time, if your team is small enough and they know what they’re doing and they’re working closely with the business and delivering working software often, then nobody cares all that much about estimating – which to be honest is how my team does a lot of our work.

But this is a problem-solving approach, not a project management approach.

If you don’t know what you are building, why estimate?

It can work for online startups and other exploratory development: you have an idea that you think is good, but you’re not sure of the details, what people are going to like and what will catch on. If you don’t really know what you are building, then there’s no point trying to estimate how long it is going to take. Somebody will decide how much money you can spend, you start simple, deliver something useful and important (“minimum viable product”) as soon as you can so you can get feedback and keep iterating until hopefully enough people are using it and are telling you what you really need to build, or you run out of money.

We’re back to Evolutionary Prototyping, but with a strict focus on minimal features and prioritization (do only what’s important, don’t even try to consider the entire project because you may not have to deliver it all anyways), and fast feedback loops. Now it’s called “The Lean Startup” method.

If you are going to change it again tomorrow, why estimate?

Working this way also makes sense for a lot of online businesses: Facebook, Twitter, Linkedin, Etsy Netflix all work this way today. They are constantly delivering small features, or maybe breaking bigger changes into small steps and pushing them out incomplete but “dark” as soon as they can (often several times a day), constantly fiddling with the UI, adding personalization features and new channels and integrating with new partners and continuously capturing behavioural data so that they can tell what changes users like or at least what they are willing to put up with, trying out new ideas and running A/B tests knowing that some or most of these ideas will fail.

This work can be done by small teams working independently, so the size and cost of each “project” is small. Marketing wants to add a new interface or run a small experiment of some kind (the details are fuzzy, we’re going to have to iterate through it), it will probably only take a few weeks or maybe a month or two, just get a few smart people together and you see how fast you can get something working. If it doesn't work, or it’s taking too long, cancel it and go on to the next idea. It’s an attention-deficit way of working, but if you are chasing after new customers or new revenue sources and your customers will put up with you experimenting with them, it can work.

Don’t bother estimating, just make it work

And routine maintenance (anything that doesn't have a fixed/drop-dead end date) can be done this way too. David Anderson’s most persuasive arguments in favor of Kanban (working without estimates and continuously pushing out individual pieces of work) are in streamlining maintenance and operations work.

The business doesn't care that much about how this kind of work is managed – they just want important things fixed ASAP, and at the least possible cost. Most of this work is done by individuals or small teams, so again the cost of any piece of work is small. Instead of wasting time trying to estimate each change or fix upfront, you assume everything takes 3 days or whatever to do, and if you aren't finished at 3 days, then stop and escalate it to management, let them review and decide whether the work needs more scoping or should be done at all. Focus on getting things done and everybody is happy.

Why bother estimating – it’s just another mobile app

And it works for mobile app development, again where most work is done by small teams and most of the focus is on the user experience, where the uncertainties are more around what customers are going to like (the product concept, the look-and-feel – which means lots of iterative design work, prototyping and usability testing... and this is going to take how long?) and not on technical risks or project risks.

But you can’t run a project without estimating

Yes a lot of work is done and can be done in small projects by small teams and if the project is small enough and short enough then you may not need to bother much or at all with estimating – because you’re not really running a project, you’re problem solving.

But this way of working doesn't scale up to large organizations running large projects and large programs with significant business and technical risks which need to be managed throughout, and work that needs to be coordinated between different teams doing lots of different things in different places at different times, with lots of handoffs and integration points and dependencies. This is where predictability – knowing where you are and seeing ahead to where you are going to be (and where everybody else is going to be) with confidence – is more important than minimizing cycle time and rapid feedback and improvisation.

It comes down to whether you need to deliver something as a big project or you can get away with solving many smaller problems instead. While there is evidence that software development projects are getting shorter on average (because people have learned that smaller projects fail less often or at least fail faster), some problems are too big to be solved piecemeal. So estimating isn’t going to go away – most of us have to understand estimating better and get better at doing it.

#NoEstimates – building software without estimating – is like Agile development in the early days. Then it was all about small teams of crackerjack programmers delivering small projects quickly (or not delivering them, but still doing it quickly) and going against the grain of accepted development methods. Agile didn’t scale, but it got a lot of buzz and achieved enough success that eventually many of the ideas crossed into the mainstream and we found ways to balance agility and discipline, so that now Agile development methods are being used successfully in even large scale programs. I don’t see how anyone can successfully manage a big project without estimating, but that doesn't mean that some people aren't going to try – I just wouldn't want to be around when they try it.

Thứ Sáu, 8 tháng 3, 2013

Book Review: The Phoenix Project

Everyone who attended the “Rugged Devops” panel at RSA this year received a free copy of The Phoenix Project (by Gene Kim, Kevin Behr and George Spafford – the authors of Visible Ops), the fictional story of the education and transformation of an IT manager, an IT organization, and eventually of an entire company.

I'm not sure why they wrote the Phoenix Project as a novel. But they did. So I’ll review it first as a piece of story telling, and then look at the messaging inside.

The reason that I don’t like didactic fiction is that so much of it is so poorly written – generally forced and artificial. I was pleasantly surprised by the Phoenix Project. The first half of the novel tells a story about an IT manager forced into taking on responsibility for saving his company. Our well-meaning hero, an ex-marine sergeant (for some reason unclear to me, the hero, the CEO, and even the mysterious guru all have a military background) with an MBA but without any ambition except to quietly provide for his family. He has been successfully running his own little part of the IT group, so successfully that he is dramatically promoted to take over all of IT operations (and so successfully that his own group is never mentioned again in the story – it seems to run on auto-pilot without him). For a successful manager, our hero knows alarmingly little about how the rest of the IT organization works, or about the business, and so is unprepared for his new responsibility. He reluctantly accepts the big job, and then regrets it immediately as he realizes what a shit storm he has walked into.

It’s a compelling narrative that draws you in and is seems realistic even with the stock characters: the sociopathic SOB CEO, the unpopular everything-by-the-book CISO, the Software Development Manager who only cares about hitting deadlines (but not about delivering software that works), the Machiavellian Marketing executive, and the autistic genius that the entire IT organization of several hundred people all depend on to get all the important stuff done or fixed.

As a pure piece of story telling, things start to unravel in the second half with the emergence of the IT / Lean Manufacturing guru – when the story ends and the devops fable begins. From this point on, the plot depends on several miraculous conversions: everyone except the marketing exec sees the light and literally transform overnight. They even start to groom themselves nicely and dress better. Lifetime friendships are made over a few drinks, and everyone learns to trust and share: there’s a particularly cringe-inducing management meeting in which people bare their souls and weep. Conflicts and problems disappear magically usually because of the guru’s intervention – including an unnecessary scene where the guru shows up at a crucial audit meeting and helps convince the partner of the audit firm (an old buddy of his) that there aren't any real problems with the company’s messed up IT controls (“these aren't the droids you’re looking for”).

But the real heroes are the people running the manufacturing group: the one part of this spectacularly mismanaged company that somehow functions perfectly is a manufacturing plant where everyone can all go to learn about Kanban and Lean process management and so on. Without the help of the smug and smart-alecky guru - who apparently helped create this manufacturing success - and his tiresome Zen master teaching approach (and sometimes even with his help), our hero is unable to understand what’s wrong or what to do about it. He doesn't understand anything about demand management, how to schedule and prioritize project work, that firefighting is actual work, how to get out of firefighting mode, how to recognize and manage bottlenecks in workflow, or even how important it is to align IT with business priorities (where did he get that MBA any ways?). Luckily, the factory is right there for him learn from, if he only opens his eyes and mind.

What will you learn from The Phoenix Project?

The other problem with this story telling approach is that it takes so damn long to get to the point – it’s a 338 page book with about 50 pages of meat. Like Goldratt's The Goal (which is referenced a couple of times in this book), The Phoenix Project leads the reader to understanding through a kind of detective story. You have to be patient and watch as the hero stumbles and goes down blind alleys and ignores obvious clues and only with help eventually figures out the answers. Unfortunately, I'm not a patient reader.

This is a gentle introduction to Lean IT and devops. If you've read anything on Kanban and devops you won’t find anything surprising, although the authors do a good job of explaining how Lean manufacturing concepts can be applied to managing IT work. The ideas covered in the book are standard Lean and Theory of Constraints stuff, with a little of David Anderson’s Kanban and some devops – especially Continuous Deployment as originally described by John Allspaw and Continuous Delivery.

The guru’s lessons are mostly about visualizing and understanding and limiting demand – that you should stop taking on more work until you can get things actually working so that you’re not spending all of your time task-switching and firefighting; identifying workflow bottlenecks and protecting or optimizing around them; how reducing batch size in development will improve control and to get faster feedback; that in order to do this you have to work on simplifying and standardizing deployment; and how valuable it is to get developers and operations to work together.

My complaints aren't with the ideas – I buy into a lot of Devops and agree that Kanban and Lean have a lot to offer to IT ops and support teams (although I'm not sold on Kanban by itself for development, certainly not at scale). But I was disappointed with the unrealistic turnaround in the second half of the book. It’s all rainbows and unicorns at the end. IT, the business, development and security all start working together seamlessly. Management is completely aligned. Performance problems? No problem – just go the Cloud. And they even bring in the famous Chaos Monkey in the last couple of pages just because.

Spoiler Art: Everything goes so well in a few months that the company is back on track, plans to outsource IT and to break up the company are cancelled, the selfish head of marketing is canned, and our hero is promoted to CIO and put on the fast track to corporate second in command. Sorry: nothing this bad gets that good that easily. It is a fable after all, and too hard to swallow.

The Phoenix Project is a unique book – when was the last time that you read an actual novel about IT management?! It was worth reading, and if it introduces devops and Lean ideas to more people in IT, The Phoenix Project will have accomplished something useful. But it’s not a book that you can use to get things done. There are lessons and recipes and patterns but they take work to pull out of the story. There’s no index, no good way to go back to find things that you thought were useful or interesting. So I am looking forward to the Devops Cookbook: something practical that hopefully explains how these ideas can work in businesses that don’t look all like Facebook and Twitter.

Thứ Ba, 27 tháng 11, 2012

Why Scrum Won

In the 1990s and early 2000s a number of different lightweight "agile" development methods sprung up.

Today a few shops use Extreme Programming, including most notably ThoughtWorks and Industrial Logic. But if you ask around, especially in enterprise shops, almost everybody who is “doing Agile” today is following Scrum or something based on Scrum.

What happened? Why did Scrum win out over XP, FDD, DSDM, Crystal, Adaptive Software Development, Lean, and all of the other approaches that have come and gone? Why are most organizations following Scrum or planning to adopt Scrum and not the Agile Unified Process or Crystal Clear (or Crystal Yellow, or Orange, Red, Violet, Magenta or Blue, Diamond or Sapphire for that matter)?

Is Scrum that much better than every other idea that came out of the Agile development movement?

Simplicity wins out

Scrum’s principal strength is that it is simpler to understand and follow than most other methods – almost naively simple. There isn't much to it: short incremental sprints, daily standup meetings, a couple of other regular and short planning and review meetings around the start and end of each sprint, some work to prioritize (or order) the backlog and keep it up-to-date, simple progress reporting, and a flat, simple team structure. You can explain Scrum in detail in a few pages and understand it less than an hour.

This means that Scrum is easy for managers to get their heads around and easy to implement, at a team-level at least (how to successfully scale to enterprise-level Scrum in large integrated programs with distributed teams using Scrum of Scrums or Communities of Practice or however you are supposed to do it, is still fuzzy as hell).

Scrum is easy for developers to understand too and easy for them to follow. Unlike XP or some of the other more well-defined Agile methods, Scrum is not prescriptive and doesn't demand a lot of technical discipline. It lets the team decide what they should do and how they should do it. They can get up to speed and start “doing Agile” quickly and cheaply.

But simplicity isn't the whole answer

But there’s more to Scrum’s success than simplicity. The real trick that put Scrum out front is certification. There’s no such thing as a Certified Extreme Programmer but there are thousands of certified ScrumMasters and certified product owners and advanced certified developers and even more advanced certified professionals and the certified trainers and coaches and officially registered training providers that certified them.

And now the PMI has got involved with its PMI-ACP Certified Agile Practitioner designation which basically ensures that people understand Scrum, with a bit of XP, Lean and Kanban thrown in to be comprehensive.

Whether Scrum certification is good or bad or useful at all is beside the point.

Certification helped Scrum succeed for several reasons. First, certification lead to early codification and standardization of what Scrum is all about. Consultants still have their own ideas and continue to fight between themselves over the only right way to do Scrum and the future direction of Scrum and what should be in Scrum and what shouldn't, but the people who are implementing Scrum don’t need to worry about the differences or get caught up in politics and religious wars.

Certification is a win win win…

Managers like standardization and certification – especially busy, risk-adverse managers in large mainstream organizations. If they are going to “do Agile”, they want to make sure that they do it right. By paying for standardized certified training and coaching on a standardized method, they can be reassured that they should get the same results as everyone else. Because of standardization and certification, getting started with Scrum is low risk: it’s easy to find registered certified trainers and coaches offering good quality professional training programs and implementation assistance. Scrum has become a product – everyone knows what it looks like and what to expect.

Certification also makes it easier for managers to hire new people (demand a certification upfront and you know that new hires will understand the fundamentals of Scrum and be able to fit in right away) and it’s easier to move people between teams and projects that are all following the same standardized approach.

Developers like this too, because certification (even the modest CSM) helps to make them more employable, and it doesn't take a lot of time, money or work to get certified.

But most importantly, certification has created a small army of consultants and trainers who are constantly busy training and coaching a bigger army of certified Scrum practitioners. There is serious competition between these providers, pushing each other to do something to get noticed in the crowd, saturating the Internet with books and articles and videos and webinars and blogs on Scrum and Scrumness, effectively drowning out everything else about Agile development.

And the standardization of Scrum has also helped create an industry of companies selling software tools to help manage Scrum projects, another thing that managers in large organizations like, because these tools help them to get some control over what teams are doing and give them even more confidence that Scrum is real. The tool vendors are happy to sponsor studies and presentations and conferences about Agile (er, Scrum), adding to the noise and momentum behind Scrum.

Scrum certification is a win win win: for managers, developers, authors, consultants and vendors.

It looks like David Anderson may be trying to do a similar thing with Kanban certification. It’s hard to see Kanban taking over the world of software development – while it’s great for managing support and maintenance teams, and helps to control work flow at a micro-level, Kanban doesn't fit for larger project work. But then neither does Scrum. And who would have picked Scrum as the winner 10 years ago?

Thứ Ba, 20 tháng 11, 2012

Predictability - Making Promises you can Keep

Speed – being first to market, rapid innovation and conducting fast cheap experiments – is critically important to startups and many high tech firms. This is where Lean Startup ideas and Continuous Deployment come in. And this is why many companies are following Agile development, to design and deliver software quickly and flexibly, incorporating feedback and responding to change.

But what happens when software – and the companies that build software – grow(s) up? What matters at the enterprise level? Speed isn't enough for the enterprise. You have to balance speed and cost and quality. And stability and reliability. And security. And maintainability and sustainability over the long term. And you have to integrate with all of the other systems and programs in your company and those of your customers and partners.

Last week, a group of smart people who manage software development at scale got together to look at all of these problems, at Construx Software’s Executive Summit in Seattle. What became clear is that for most companies, the most important factor isn’t speed, or productivity or efficiency – although everyone is of course doing everything they can to cut costs and eliminate waste. And it isn’t flexibility, trying to keep up with too much change. What people are focused on most, what their customers and sponsors are demanding, is predictability – delivering working software when the business needs it, being a reliable and trusted supplier to the rest of the business, to customers and partners.

Enterprise Agile Development and Predictability

Steve McConnell’s keynote on estimation in Agile projects kicked this off. A lot of large companies are adopting Agile methods because they’ve heard and seen that these approaches work. But they’re not using Agile out of the box because they’re not using it for the same reasons as smaller companies.

Large companies are adapting Agile and hybrid plan-based/Waterfall approaches combining upfront scope definition, estimating and planning, with delivering the project incrementally in Agile time boxes. This is not about discovery and flexibility, defining and designing something as you go along – the problems are too big, they involve too many people, too many parts of the business, there are too many dependencies and constraints that need to be satisfied. Emergent design and iterative product definition don’t apply here.

Enterprise-level Agile development isn’t about speed either, or “early delivery of value”. It’s about reducing risk and uncertainty. Increasing control and visibility. Using story points and velocity and release Burn Up reporting and evidence of working software to get early confidence about progress on the project and when the work will be done.

The key is to do enough work upfront so that you can make long-term commitments to the business – to understand what the business needs, at least at a high level, and estimate and plan this out first. Then you can follow Agile approaches to deliver working software in small steps, and to deal with changes as they come in. As McConnell says, it’s not aboutresponding to change over following a plan”. It’s having a plan that includes the ability to respond to change.

By continuously delivering small pieces of working software, and calibrating their estimates with real project data using velocity, a team working this way will be able to narrow the “cone of uncertainty” much faster – they’ll learn quickly about their ability to deliver and about the quality of their estimates, as much as 2x faster than teams following a fully sequential Waterfall approach.

There are still opportunities to respond to change and reprioritize. But this is more about working incrementally than iteratively.

Kanban and Predictability

Enterprise development managers are also looking at Kanban and Lean Development to manage waste and to maintain focus. But here too the value is in improving predictability, to smooth work out and reduce variability by finding and eliminating delays and bottlenecks. It’s not about optimization and Just-in-Time planning.

As David Anderson explained in his keynote on Delivering Better Predictability, Business Agility and Good Governance with Kanban, senior executives care about productivity, cost and quality – but what they care about most is predictability. The goal of a good software development manager is to be able to make a customer promise that their organization can actually meet.

You do this by keeping the team focused on the business of making software, and trying to drive out everything else: eliminating delays and idle time, cutting back administrative overhead, not doing work that will end up getting thrown away, minimizing time wasted in multi-tasking and context-switching, and not starting work before you’ve finished the work that you’ve already committed to. Anderson says that managers like to start on new work as it comes in because “starting gives your customer a warm comfortable feeling” – until they find out you’ve lied to them, because “we’re working on it” doesn’t mean that the work is actually getting done, or will ever get done. This includes fixing bugs – you don’t just fix bugs right away because you should, you fix bugs as they’re found because the work involved is smaller and more predictable than trying to come back and fixing them later.

Teams can use Kanban to dynamically prioritize and control the work in front of them, to balance support and maintenance requirements against development work and fixed date commitments with different classes of service, and limit Work in Progress (WIP) to shorten lead times and improve throughput, following the Theory of Constraints. This lets you control variability and improve predictability at a micro-level. But you can also use actual throughput data and Cumulative Flow reporting to project forward on a project level and understand how much work the team can do and when they will be done.

What’s interesting to me is seeing how the same ideas and methods are being used in very different ways by very different organizations – big and small – to achieve success, whether they are focused on fast iterations and responding to rapid change, or managing large programs towards a predictable outcome.

Thứ Năm, 13 tháng 9, 2012

Can you get by without estimating? Should you try?

Estimating remains one of the hardest problems in software development. So hard in fact that more people lately are advocating that we shouldn’t bother estimating at all.

David Anderson, the man behind Kanban, says that we should stop estimating, and that estimates are a waste of time. In his case study about introducing Kanban ideas at Microsoft, one of the first steps that they took to improve a team’s productivity was to get them to stop estimating and start focusing instead on prioritizing work and getting the important work done.

Then you have experts like Ron Jeffries saying things like

I believe that most estimation is waste and that it is more common to use estimation as a replacement for proper steering, and to use it as a whip on the developers, than it is to use it for its only valid purpose in Release Planning, which is more like "decide whether to do this project" than "decide just how long this thing we just thought of is going to take, according to people who don't as yet understand it or know how they'll do it”

and

Estimation is clearly "waste". It's not software…If estimation IS doing you some good, maybe you should think about it as a kind of waste, and try to get rid of it.

And, from others on the “If you do bother estimating, there’s no point in putting a lot of effort into it” theme:

Spending effort beyond some minutes to make an estimate "less wrong" is wasted time. Spending effort calculating the delta between estimates and actuals is wasted time. Spending effort training, working and berating people to get "less wrong" estimates is wasted time and damaging to team performance.

In “Software estimation considered harmful?” Peter Seibel talks about a friend running a startup, who found that it was more important to keep people focused and motivated on delivering software as quickly as possible. He goes on to say

If the goal is simply to develop as much software as we can per unit time, estimates (and thus targets), may be a bad idea.

He bases this on a 1985 study in Peopleware which showed that programmers were more productive when working against their own estimates than estimates from somebody else, but that people were most productive on projects where no estimates were done at all.

Seibel then admits that maybe “estimates are needed to coordinate work with others” – so he looks at estimating as a “tool for communication”. But from this point of view, estimates are an expensive and inefficient way to communicate information that is of low-quality – because of the cone of uncertainty all estimates contain variability and error anyways.

What’s behind all of this?

Most of this thinking seems to come out of the current fashion of applying Lean to everything, treating anything that you do as potential waste and eliminating waste wherever you find it. It runs something like: Estimating takes time and slows you down. You can’t estimate perfectly anyways, so why bother trying?

A lot of this talk and examples focus on startups and other small-team environments where predictability isn’t as important as delivering. Where it’s more important to get something done than to know when everything will be done or how much it will cost.

Do you need to estimate or not?

I can accept that estimates aren’t always important in a startup – once you’ve convinced somebody to fund your work anyways.

If you’re firefighting, or in some kind of other emergency, there’s not much point in stopping and estimating either – when it doesn’t matter how much something costs, when all you care about is getting whatever it is that you have to do done as soon as possible.

Estimating isn’t always important in maintenance – the examples where Kanban is being followed without estimating are in maintenance teams. This is because most maintenance changes are small by definition - maintenance is usually considered to be fixing bugs and making changes that take less than 5 days to complete. In order to really know how long a change is going to take, you need to review the code to know what and where to make changes. This can take up to half of the total time of making the change – and if you’re already half way there, you might as well finish the job rather than stopping and estimating the rest of the work. Most of the time, a rule of thumb or placeholder is a good enough estimate.

In my job, we have an experienced development team that has been working on the same system for several years. Almost all of the people were involved in originally designing and coding the system and they all know it inside-out.

The development managers triage work as it comes in. They have a good enough feel for the system to recognize when something looks big or scary, when we need to get some people involved upfront and qualify what needs to get done, work up a design or a proof of concept before going further.

Most of the time, developers can look at what’s in front of them, and know what will fit in the time box and what won’t. That’s because they know the system and the domain and they usually understand what needs to be done right away – and if they don’t understand it, they know that right away too. The same goes for the testers – most of the time they have a good idea of how much work testing a change or fix will take, and whether they can take it on.

Sure sometimes people will make mistakes, and can’t get done what they thought they could and we have to delay something or back it out. But spending a little more time on analysis and estimating upfront probably wouldn't have changed this. It’s only when they get deep into a problem, when they’ve opened the patient up and there’s blood everywhere, it’s only then that they realize that the problem is a lot worse than they expected.

We’re not getting away without estimates. What we’re doing is taking advantage of the team’s experience and knowledge to make decisions quickly and efficiently, without unnecessary formality.

This doesn't scale of course. It doesn’t work for large projects and programs with lots of inter-dependencies and interfaces, where a lot of people need to know when certain things will be ready. It doesn’t work for large teams where people don’t know the system, the platform, the domain or each other well enough to make good quick decisions. And it’s not good enough when something absolutely must be done by a drop dead date – hard industry deadlines and compliance mandates. In all these cases, you have to spend the time upfront to understand and estimate what needs to get done, and probably re-estimate again later as you understand the problem better. Sometimes you can get along without estimates. But don’t bet on it.

Thứ Ba, 14 tháng 8, 2012

What can you get out of Kanban?

I’ve spent the last year or so learning more about Kanban, how to use it in software development and IT operations.

It’s definitely getting a lot of attention, and I want to see if it can help our development and operations teams work better.

What to Read, What to Read?

There’s a lot to read on Kanban – but not all of it is useful. You can be safe in ignoring anything that tries to draw parallels between Japanese manufacturing and software development. Anyone who does this doesn’t understand Lean manufacturing or software development. Kanban (big K) isn’t kanban (little k) and software development isn’t manufacturing.

Kanban in software development starts with David Anderson’s book. It’s heavy on selling the ideas behind Kanban, but unfortunately light on facts and examples – mostly because there wasn’t a lot of experience and data to draw on at the time the book was written. Everything is built up from two case studies in small maintenance organizations.

The first case study (which you can read here online) goes back to 2005, at a small offshore sustaining engineering team in Microsoft. This team couldn’t come close to keeping up with demand, because of the insanely heavyweight practice framework that they were following (CMMI and TSP/PSP) and all of the paperwork and wasted planning effort that they were forced to do. They were spending almost half of their time on estimating and planning, and half of this work would never end up being delivered because more work was always coming in.

Anderson and another Microsoft manager radically simplified the team’s planning, prioritization and estimation approach, cutting out a lot of the bullshit so that the team could focus instead on actually delivering what was important to the customers.

You can skip over the theory – the importance of Drum-Buffer-Rope – Anderson changed his mind later on the theory behind the work anyways. As he says:

“This is a case study about implementing common sense changes where they were needed”.

The second case study is about Anderson doing something similar with another ad hoc maintenance team at Corbis a couple of years later. The approach and lessons were similar, in this case focusing more on visual tracking of work and moving away from time boxing for maintenance and break/fix work, using explicit WIP limits instead as the forcing function to control the team’s work.

The rest of the book goes into the details of tracking work on task boards, setting and adjusting limits, and just-in-time planning. There’s also some discussion of effecting organizational change and continuous improvement, which you can get from any other Agile/Lean source.

Corey Ladas’ book Scrumban is a short collection of essays on Kanban and combining Scrum and Kanban. The book is essentially built around one essay, which, taking a Lean approach to save time and money, I suggest that you read here instead. You don’t need to bother with the rest of the book unless you want to try and follow along as Ladas works his ideas out in detail. The basic ideas are the same as Anderson (not surprising, since they worked together at Corbis):

Don’t build features that nobody needs right now. Don’t write more code than you can test. Don’t test more code than you can deploy.

David Anderson has a new book on Kanban coming out soon Unfortunately it looks like a rehash of some of his blog posts with updated commentary. I was hoping for something with more case studies and data, and follow-ups on the existing case studies to see if they were able to sustain their success over time.

There is other writing on Kanban, by excited people who are trying out (often in startups or small teams), or by consultants who have added Kanban to the portfolio of what they are selling – after all, “Kanban is the New Scrum”.

You can keep up with most of this through the Kanban weekly Roundup, which provides a weekly summary of links and discussion forums and news groups and presentations and training in Kanban and Lean stuff. And there’s a discussion group on Kanban development which is also worth checking out. But so far I haven’t found anything, on a consistent basis anyways, that adds much beyond what you will learn from reading Anderson’s first Kanban book.

Where does Kanban work best?

Kanban was created to help break/fix maintenance and sustaining engineering teams. Kanban’s pull-based task-and-queue work management matches the unpredictable, interrupt-driven and specialized work that these teams do. Kanban puts names and a well-defined structure around common sense ideas that most successful maintenance and support and operations teams already follow, which should help inexperienced teams succeed. It makes much more sense to use Kanban than to try to bend Scrum to fit maintenance and support, or following a heavyweight model like IEE 1219 or whatever it is being replaced by.

I can also see why Kanban has become popular with technology startups, especially web / SaaS startups following Continuous Deployment and a Lean Startup model. Kanban is about execution and continuous optimization, removing bottlenecks and reducing cycle time and reacting to immediate feedback. This is exactly what a startup needs to do once they have come up with their brilliant idea.

But getting control over work isn’t enough, especially over the longer-term. Kanban’s focus is mostly tactical, on the work immediately in front of the team, on identifying and resolving problems at a micro-level. There’s nothing that gets people to put their heads up and look at what they can and should do to make things better on a larger-scale – before problems manifest themselves as delays. You still need a layer of product management and risk management over Kanban, and you’ll also need a technical software development practice framework like XP.

I also don’t see how – or why – Kanban makes much of a difference in large-scale development projects, where flow and tactical optimization aren’t as important as managing and coordinating all of the different moving pieces. Kanban won’t help you scale work across an enterprise or manage large programs with lots of interdependencies. You still have to do project and program and portfolio management and risk management above Kanban’s micro-structure for managing day-to-day work, and you still need a SDLC.

Do you need Kanban?

Kanban is a tool to solve problems in how people get their work done. Anderson makes it clear that Kanban is not enough in itself to manage software development regardless of the size of the organization – it’s just a way for teams to get their work done better:

“Kanban is not a software development life cycle or a project management methodology…You apply a Kanban system to an existing software development process…”

Kanban can help teams that are being crushed under a heavy workload, especially support and maintenance teams. Combining Kanban with a triage approach to prioritization would be a good way to get through a crisis.

But I don’t see any advantage in using Kanban for an experienced development team that is working effectively.

Limiting Work in Progress? Time boxing already puts limits around the work that development teams do at one time, giving the team a chance to focus and get things done.

Although some people argue that iterations add too much overhead and slow teams down, you can strip overheads down so that time boxing doesn’t get in the way - so that you really are sprinting.

Getting the team to understand the flow of work, making delays and blockers visible and explicit is an important part of Kanban. But Microsoft’s Eric Brechner (er, I mean, “I. M. Wright”) explains that you don’t need Kanban and taskboards to see delays and bottlenecks or to balance throughput in an experienced development team:

“Good teams do this intuitively to avoid wasted effort. They ‘right-size’ their teams and work collaboratively to succeed together.”

And anybody who is working iteratively and incrementally is already doing or should be doing just-in-time planning and prioritization.

So for us, Kanban doesn’t seem to be worth it, at least for now. If your development team is inexperienced and can’t deliver (or don’t know what they need to deliver), or you’re in a small maintenance or firefighting group, Kanban is worth trying. If Kanban can help operations and maintenance teams survive, and help some online startups launch faster, if that’s all that people ever do with Kanban, the world will still be a better place.

Thứ Năm, 21 tháng 6, 2012

Sooner or Later: Deliver Early or Minimize Waste

There’s an obvious but important tension in Lean/Agile development around when to make decisions. Between the fundamental Agile position that we should do the most important and most risky work first, and the Lean argument that we should make decisions at the last possible moment. We need to decide early and try things out, iterate to minimize risk and time to market; but we should put off decisions and avoid iterating to keep costs down.

Later is better than sooner

Lean Development says that in order to avoid waste, we should wait to make decisions as late as possible, especially when we think the stakes may be high. The later that you can make a decision, the more information that you will have on hand to inform your decision, and the more options that you will have to choose from. This means that you should be able to make better quality decisions.

Deferred decision making is built into incremental/iterative planning and management. You don’t try to anticipate everything up front. You don’t try to work out all of the details and dependencies and resourcing at the beginning. Instead, you sketch out an outline of a plan with all of the critical dependencies and milestones that you know about, then focus on what’s in front of you as you move ahead. Detailed decisions about scheduling and implementation and re-prioritization are made when you are ready to do the work, just-in-time.

Deciding later costs less

In Agile Estimating and Planning,Mike Cohn says that

“The best way to reduce the cost of change is to implement a feature as late as possible – effectively when there is no more time for change”.
Because you are putting off work until later, there’s less chance that new information will come up and force you to change something that you’ve already decided on. Procrastination pays – or, at least, it saves some time and money.

You don’t want to put a lot of work into something until you know as much as you can about what you need to do, how you need to do it, or even if you really do need to do it. Build a prototype or run a technical spike first, build a first-of and maybe a second-of something and get the customer using it, get feedback and make sure you have a good idea of what you are doing before you do more typing. This is good common sense.

And there is other work that you can put off because you don’t have to worry about it – you have to do it, but you know what you need to do and you know that you can do it. You might as well wait until you have fleshed out more of the system first so that you can get it done quickly.

When should you do decide sooner rather than later?

The kind of work that you can afford to put off safely is mostly obvious. And the kind of work that you can’t put off to later is also obvious, like figuring out the basic architecture, the platforms and languages that you are going to use, the basic approach that you are going to follow, proving out your core ideas. These are decisions that you need to make early on, while there is still time to learn and while there is still time to change your mind and start again if you have to.

That’s why I was surprised by the example that Mike Cohn uses in his book:

“Adding support for internationalization today may take four weeks of effort; adding it in six months may take six weeks. So we should add it now, right? Maybe. Suppose we spend four weeks and do it now. Over the next six months, we may spend an additional three weeks changing the original implementation based on knowledge gained during that six months. In that case, we would have been better off waiting. Or what if we spend four weeks now and later discover that a simpler and faster implementation would have been adequate?”
But internationalization is a cross-cutting concern. This kind of work is often much harder to take care of than you want it to be or think it will be, impacting more of the design and code than you expect. Do you really want to wait six months before you find out that you have to change all of the forms and reports that you have developed to handle LTR and RTL languages simultaneously, or properly take care of laying out Japanese and Chinese characters? I’ve spent several weeks working with internationalization experts just trying to understand and solve problems with rendering honorific marks in Arabic names (a small thing, but a deal-killer if you are working with Middle Eastern royalty).

Other cross-cutting concerns may require much more fundamental and more expensive changes to implement later, changes that are hard to get right and hard to test: data validation, security, monitoring and instrumentation, caching, logging, error handling, persistence. Understanding this upfront and supporting it from the start is much less risky and less costly than trying to “add it in later”.

When in doubt, sooner is better than later

Deciding to do something early means that you are probably going to make mistakes and you will have to throw some work away, and you’re going to have to make changes later when you get more information. All of this is waste.

When it comes to planning out details, putting off decisions to just-in-time makes sense. But when it comes to designing and implementing important parts of the system, especially technical plumbing and cross-cutting work, doing something sooner is almost always better than later. Managing risk upfront will save you more money in the end.

Thứ Ba, 29 tháng 11, 2011

Iterationless Development – the latest New New Thing

Thanks to the Lean Startup movement, Iterationless Development and Continuous Deployment have become the New New Thing in software development methods. Apparently this has gone so far that “there are venture firms in Silicon Valley that won’t even fund a company unless they employ Lean startup methodologies”.

Although most of us don’t work in a Web 2.0 social media startup, or anything like one, it’s important to cut through the hype and see what we can learn from these ideas. One of the most comprehensive descriptions I’ve seen so far of Iterationless Development is a (good, but buzzword-heavy) presentation by Erik Huddleston that explains how development is done at Dachis Group, which builds online social communities. The development team’s backlog is updated on a just-in-time basis, and includes customer business requirements (defined as minimum features), feedback from Operations (data from analytics and results of Devops retrospectives), and minimally required technical architecture.

Work is managed using Kanban WIP limits and queues. Developers create tests for each change or fix up front. Every check-in kicks off automated tests and static analysis checks for complexity and code duplication as part of Continuous Integration. If it passes these steps, the change is promoted to a test environment, and the code must then be reviewed for architectural oversight (they use Atlassian’s Crucible online code review tool to do this).

Once all of the associated change sets have been reviewed, the code changes are deployed to staging for acceptance testing and review by product management, before being promoted to production. All production changes (code change sets, environment changes and database migration sets) are packaged into Chef recipes and progressively rolled out online. It’s a disciplined and well-structured approach that depends a lot on automation and a good tool set.

Death to Time Boxing

What makes Iterationless Development different is obviously the lack of time boxing – instead of being structured in sprints or spikes, work is done in a continuous flow. According to Huddleston, iterationless Kanban is “here to stay” and is “much more productive than artificial time boxing”.

In a separate blog post, he talks about the death of iterations. While he agrees that iterations have benefits – providing a fixed and consistent routine for the team to follow, a forcing function to drive work to conclusion (nothing focuses the mind like a deadline), and logical points for the team to synch up with the rest of the business – Huddleston asserts that working in time boxes is unnatural and unnecessary. That the artificial and arbitrary boundaries defined by time boxes force people to compromise on solutions, and force them to cut corners in order to meet deadlines.

I agree that time boxes are arbitrary – but no more arbitrary than a work day or work week, or a month or a financial quarter; all cycles that businesses follow. In business we are always working towards a deadline, whether it is hard and real or soft and arbitrary. This is how work gets done. And this doesn’t change if we are working in time boxes or without them.

In iterationless Kanban, the pressure to meet periodic time box deadlines is replaced with the constant pressure to deliver work as fast as possible, to meet individual task deadlines. Rapid cycling in short time boxes is hard enough on teams over a long period of time. Continuous, interrupt-driven development with a tight focus on optimizing cycle time is even harder. The dials are set to on and they stay that way. Kanban makes this easy, giving the team, and the customer and management, the tools to continuously visualize work in progress, identify bottlenecks and delays and squeeze out waste – to maximize efficiency. This is a manufacturing process model remember. The emphasis on tactical optimization and fast-feedback loops, and the “myopic focus on eliminating waste” is just that – short-sighted and difficult to sustain.

With time boxes there are at least built-in synch points, chances for the team to review and reset, so that people can reflect on what they have done, look for ways to improve, look ahead at what they need to do next, and then build up again to an optimal pace. This isn’t waste. Cycling up and down is important and necessary to keep people from getting burnt out and to give them a chance to think and to get better at what they do.

Risk is managed in the same tactical, short-sighted way. Teams working on one issue at a time end up managing risk one issue at a time, relying heavily on automated testing and in-stream controls like code reviews. This is good, but not good enough for many environments: security and reliability risks need to be managed in a more comprehensive, systemic way. Even integrating feedback from Ops isn’t enough to find and prevent deep problems. Working in Agile time boxes is already trading technical risks for speed and efficiency. Iterationless Development and Continuous Deployment, focused on eliminating waste and on accelerating cycle time, pushes these tradeoffs even further, into the danger zone.

Huddleston is also critical of “boxcaring” – batching different pieces of work together in a time box – because it interferes with simple prioritization and introduces unnecessary delays. But batching work together that makes sense to do together can be a useful way to reduce risk and cost. Take a simple example. The team is working on feature 1a . Once it's done, they move on to feature 1b, then 1c. All of this work requires changing the same parts of code, the same or similar testing and reviews, and has a similar impact on operations. By batching this work together, you might deliver it slower, but you can reduce waste and minimize risk by delivering it once, rather than 3 times.

Iterationless Development Makes Sense…

Iterationless Development using Kanban as a control structure is an effective way to deal with excessive pressure and uncertainty – like in an early-stage startup, or a firefighting support team. It’s good for rapid innovation and experimental prototyping, building on continuous feedback from customers and from Operations – situations where speed and responsiveness to the business and customers is critical, more important than minimizing technical and operational risks. It formalizes the way that most successful web startups work – come up with a cool idea, build a prototype as quickly as possible, and then put it out and find out what customers actually want before you run out of cash. But it’s not a one-size-fits-all solution to software development problems.

All software development methods are compromises – imperfect attempts at managing risks and uncertainty. Sequential or serial development methods attempt to specify and fix the solution space upfront, and then manage to this fixed scope. Iterative, time-boxed development helps teams deal with uncertainty by breaking business needs down into small, concrete problems and delivering a working solution in regular steps. And iterationless, continuous-flow allows teams to rapidly test ideas and alternatives, when the problem isn’t clear and nobody is sure yet what direction to go in.

There’s no one right answer. What approach you follow depends on what your priorities and circumstances are, and what kind of problems and risks you need to solve today.